Project Overview
Recommend to supply and install new Faac B680 barrier to replace damage unit and new concrete fixing plinth. Allowing existing wiring to locate into new barrier.
First visit: remove barrier and lock off isolation.
- Excavate concrete fixing plinth and dispose of responsibly.
- Install new concrete fixing plinth with existing wiring duct in the centre.
Second visit: supply and install new barrier system and wire accordingly.
- Commission and test.
All works were completed on 23/09/2025.
Works Completed
- Removed the damaged barrier unit during the first visit and safely isolated the power supply
- Excavated and removed the existing concrete fixing plinth, disposing of all waste responsibly
- Installed a new concrete fixing plinth with the existing wiring duct positioned centrally for correct alignment
- Returned for the second visit once the concrete had set to supply and install the new FAAC B680 barrier system
- Wired the new barrier into the existing services and carried out full commissioning
- Tested all functions to ensure smooth and reliable operation
- Left the barrier fully operational and the site clean and tidy